.
Search the Suffolk Coastal website
Thorpeness erosion response works

Rate this page as Good Rate this page as Average Rate this page as Poor

How do you rate this information or service?

Website approved by the Plain English Campaign

Thorpeness erosion response works

In October 2010 work got underway on a community partnership scheme involving Suffolk Coastal to provide protection to part of our threatened coastline at Thorpeness.

The phase 1 emergency protection works were completed in February 2011. An extended phase 2 of the works started on site in September 2011 and was completed on 3 February 2012.

Phase 2 works

Phase 2 involved strengthening the existing failed gabion (rock-filled wire baskets) structure using a combination of sand filled geo-textile bags and localised rock infill.

J Breheny Contractors Ltd laid a grand total of 1,856 bags, eight to ten layers deep, on over one and a half square miles of geo-fabric. This has created a 600 foot toe-shaped structure that will provide vital support to the existing structure. Work was due to be finished by mid-January but has been completed two weeks earlier than expected.

As the bag laying was completed early and some money was saved, some additional work was done to repair and reinforce the existing gabions meaning that work extended into early February. More information about that work can be found in the December newsletter below.

Owen Evans is the site supervisor for J Breheny Contractors Limited. If you see anything unsafe or damaged, he can be contacted on 07771 635177.

The project has seen a range of partners involved, with the Environment Agency and Natural England being very supportive in the planning and design stages, along with local landowners Suffolk County Council and the Ogilvie Estate.

There has been very close liaison throughout the two phases with community representatives which has proved invaluable and has built strong links which will help monitor and manage the works in future.

Most of the funding was from the Government via the Environment Agency, with the remainder coming from Suffolk Coastal and most importantly local residents, as without their £137,000 commitment the scheme would not have got financial backing from the Government.

Drawings of the scheme can be viewed below:

An intial assessment of the cost and benefits of this further work can be found below:

Thorpeness coastal analysis report July 2011

The report below was carried out following the completion of the Phase 1 works, to look at how coastal processes affect the beach at Thorpeness, and whether the beach recycling works carried out during Phase 1 had any detrimental impact on the Ness.

Phase 1 emergency protection works

Phase 1 emergency protection works complete February 2011

Cliff erosion July 2010

Heavy storms and unusual weather patterns through May and June 2010 gave the foreshore such a pounding that tonnes of material was swept out to sea, revealing a series of gabions (rock-filled wire baskets) that had been in place since 1976 to help protect the coastline. The weather also worsened erosion of a previously eroding unprotected cliff face to the north of the existing defences.

Immediate emergency action was taken to contain the damage and stop the rapid erosion and so help safeguard nearby homes. Contactors placed new gabions in front of the cliff where the main erosion took place although works to defend the cliff at its closest point to the properties were destroyed by severe weather

While there was a partial recovery in beach levels, the local community, Suffolk Coastal’s coast protection team, the Environment Agency and Natural England worked together to develop a lasting solution to this dramatic erosion.

It is thanks to the efforts of the local community in raising £72,000 that allowed the works to begin as there were no other sources of national funding available. Suffolk Coastal contributed £30,000 to the scheme.

A 'soft toe' construction built from large geo-textile bags filled with sand and shingle has been put in place in the first phase of the emergency protection works. Bag laying operations were completed in December 2010 and work to cover the bags with shingle dug from the Ness was finished in February 2011.

W3C CSS validator (new window) | W3C XHTML validator (new window) |W3C accessibility guidelines (new window)
© Suffolk Coastal District Council. | Legal & privacy | Site statistics